Update - 09 October 2024
Updated project programme
Please see below for an updated project programme as of 9 October 2024.
| Activity | Start | End |
|---|---|---|
| DCO application preparation | ||
| Ecology surveys | January 22 | March 25 |
| Stage Three Statutory Consultation | 14th October 24 | 19th November 24 |
| Consultation analysis and response preparation | November 24 | December 24 |
| Consultation report development | December 24 | December 24 |
| Adequacy of consultation milestone application | December 24 | |
| ES Design Freeze | December 24 | |
| Draft DCO application documents | April 24 | March 25 |
| Final ES chapters | October 24 | March 25 |
| DCO application submitted | March 25 | |
| DCO decision received | July 26 | |
| PINS engagement | ||
| Document review | December 24 | February 25 |
| PINS meeting #1 | December 24 | |
| Topic based meeting #1 | December 24 | |
| PINS meeting #2 | January 25 | |
| Topic based meeting #2 | January 25 | |
| PINS meeting #3 | February 25 | |
| Topic based meeting #3 | February 25 | |
| PINS meeting #4 | March 25 | |
| Topic based meeting #4 | March 25 | |
| HSE | ||
| HSE review of Final Safety Case | June 26 | December 27 |
| Detailed Design and Construction | ||
| Detailed design | July 25 | February 27 |
| Land liaison for construction works | January 26 | February 27 |
| Site mobilisation | February 27 | May 27 |
| Main construction | April 27 | December 29 |
| Operation | ||
| Commissioning complete and operation commences | Spring 2030 | |