Programme update
Programme update
| Activity | Start | End |
|---|---|---|
| DCO application preparation | ||
| Application Ecology surveys (pre construction surveys will also be completed) | January 22 | May 25 |
| Targeted consultation | Late January 25 | Late February 25 |
| Adequacy of consultation milestone application | January 25 | |
| Draft DCO application documents | April 24 | May 25 |
| Final ES chapters | October 24 | May 25 |
| DCO application submitted | Autumn 25 | |
| DCO decision received | Winter 26/27 | |
| PINS engagement | ||
| Document review | March 25 | April 25 |
| Topic based meeting #1 | January 25 | |
| PINS meeting #2 | February 25 | |
| PINS meeting #3 | March 25 | |
| PINS meeting #4 | April 25 | |
| HSE | ||
| HSE review of Safety Case | July 26 | December 28 |
| Detailed Design and Construction | ||
| Detailed design | 2026 | 2027 |
| Land liaison for construction works | 2026 | 2029 |
| Site mobilisation | 2027 | 2029 |
| Main construction | 2027 | 2029 |
| Operation | ||
| Commissioning complete and operation commences | 2030 | |